Question
Question 1. Question :
A graph that plots the total resources needed per period vs. time is called a(n) __________.
: Gantt Chart
Resource Loading Chart
Work Breakdown Structure
Project Network Chart
PERT/CPM Chart
Question 2. Question :
Considering the following Activity-On-Node (AON) project (activity completion times are in days), what is the slack time associated with activity E?
Activity-On-Node
Click here to view a Word version of the project.
0 days
1 day
2 days
3 days
3 of 3
Question 3. Question :
Considering the following Activity-On-Node (AON) project (activity completion times are in days), how long will it take to complete the project?
Activity-On-Node
Click here to view a Word version of the project.
13 days
14 days
15 days
16 days
3 of 3
Question 4. Question :
Consider the following Activity-On-Node (AON) PERT project. The three values that represent each activity’s completion time (in days) correspond to an optimistic time, most likely time, and pessimistic time, respectively. What is the standard deviation associated with the completion time of activity B?
Activity-On-Node-2
Click here to view a Word version of the project.
0.0245 days
0.6667 days
0.3145 days
0.3333 days
3 of 3
Question 5. Question :
Consider the following Activity-On-Node (AON) PERT project. The three values that represent each activity’s completion time (in days) correspond to an optimistic time, most likely time, and pessimistic time, respectively. What is the expected completion time of activity A?
Activity-On-Node-2
Click here to view a Word version of the project.
2 days
3 days
4 days
5 days
3 of 3
Question 6. Question :
Jamie is planning a trip overseas. A variety of activities must be completed before her departure. The following table describes the relationships between these activities:
Immediate
Activity Predecessors
A –
B A
C A
D B, C
E B, C
F D, E
G F
Jamie was also able to estimate the activity times as shown in the table below:
Activity Time (Days)
A 4
B 4
C 5
D 3
E 3
F 2
G 1
Considering the information above, what is the length of the project?
11 days
12 days
14 days
15 days
3 of 3
Question 7. Question :
Consider the following set of activities that must be completed in order to prep a new home for painting:
Immediate
Activity Predecessors
A –
B –
C A, B
D C
E C
F D, E
G E
H F, G
Also assume that the painters were able to estimate the activity times as shown in the table below:
Activity Time (Days)
A 3
B 2
C 4
D 5
E 3
F 2
G 4
H 2
Considering the information above, what is the earliest finish time for activity F?
10 days
12 days
14 days
16 days
3 of 3
Question 8. Question :
Consider the following set of activities that must be completed in order to prep a new home for painting:
Immediate
Activity Predecessors
A –
B –
C A, B
D C
E C
F D, E
G E
H F, G
Also assume that the painters were able to estimate the activity times as shown in the table below:
Activity Time (Days)
A 3
B 2
C 4
D 5
E 3
F 2
G 4
H 2
Considering the information above, what is the critical path?
ACDFH
IN ACEFH
BCDFH
BCEGH
0 of 3
Question 9. Question :
Francisco is planning a vacation to Germany. A variety of activities must be completed before his departure. The following table describes the relationships between these activities:
Immediate
Activity Predecessors
A –
B –
C –
D A, B
E C
F D, E
G E
H F, G
I F
J I, H
Francisco was also able to estimate the activity times as shown in the table below:
Activity Time (Days)
A 3
B 4
C 5
D 3
E 2
F 1
G 4
H 3
I 2
J 5
Considering the information above, what is the slack for activities F and G respectively?
0 days; 0 days
3 days; 0 days
4 days; 3 days
4 days; 0 days
3 of 3
Question 10. Question :
Francisco is planning a vacation to Germany. A variety of activities must be completed before his departure. The following table describes the relationships between these activities:
Immediate
Activity Predecessors
A –
B –
C –
D A, B
E C
F D, E
G E
H F, G
I F
J I, H
Francisco was also able to estimate the activity times as shown in the table below:
Activity Time (Days)
A 3
B 4
C 5
D 3
E 2
F 1
G 4
H 3
I 2
J 5
Considering the information above, what is the earliest finish time for activity E?
5 days
6 days
7 days
8 days
3 of 3
* Times are displayed in (GMT-05:00) Eastern Time (US & Canada)
Assignmentsonline.org help students to solve their assignment in the best possible manner. In the assignment help industry, we are regarded as one of the best helpers for students’ tasks in all subjects. We provide solutions to students from all corners of the world, but the main focus is from students residing in the US, UK, and Australia. Our primary focus is solving student assignments for all subjects and streams.