2024 – accounting class use excel to solve this problem Waterways has two major public park projects to provide with comprehensive

Waterways has two major public-park projects to provide with comprehensive irrigation in one of its service locations this month. Job J57 and Job K52 involve 15 acres of landscaped – 2024

accounting class. use excel to solve this problem

 

Waterways has two major public-park projects to provide with comprehensive irrigation in one of its service locations this month. Job J57 and Job K52 involve 15
acres of landscaped terrain which will require special-order sprinkler heads to meet the specifications of the project. Using a job cost system to produce these parts, the following events occurred during December 2012. Raw materials were requisitioned from
the company’s inventory on December 2 for $5,061; on December 8 for $1,059; and on December 14 for $3,459. In each instance, twothirds (2/3) of these materials were for J57 and the rest for K52. Six time tickets were turned in for these two projects for a
total amount of 18 hours of work. All the workers were paid $16.50 per hour. The time tickets were dated December 3, December 9, and December 15. On each of those days, 6 labor hours were spent on these jobs, two-thirds (2/3) for J57 and the rest for K52.
The predetermined overhead rate is based on machine hours. The expected machine hour use for the year is 2,112 hours, and the anticipated overhead costs are $840,576 for the year. The machine were used by workers on projects K52 and J57 on December 3, 9, and
15. Six machine hours were used for project K52 (2 each day), and 8.5 machine hours were used for project J57 (2.5 the first day and 3 each of the other days). Both of these special orders were completed on December 15, producing 237 sprinkler heads for J57
and 142 sprinkler heads for K52. Additional job order activities during this period of time included: Dec. 1 Purchased raw materials from Durbin Supply Company on account for $53,200. Dec. 2 Issued $40,000 of direct materials from the company’s inventory to
jobs other than K52 and J57 and $3,000 of indirect materials. Dec. 12 Paid Waterways’ factory salaries and wages in the amount of $65,000. Dec. 13 Paid the factory’s water bill of $9,000. Dec. 18 Transferred $50,000 of costs from other completed jobs to finished
goods. Dec. 21 Paid the factory’s electric bill of $12,000 for Waterways’ factory. Dec. 31 Made adjusting entries for the factory that included accrued property taxes of $12,000, prepaid insurance of $8,800, and accumulated depreciation of $16,000. Instructions
(a) Set up the job cost sheets for Job No. J57 and Job No. K52. Determine the total cost for each manufacturing special order for these jobs. (Round unit cost to nearest cent.) (b) Journalize the activities from these job cost sheets in the general journal.
Also journalize the other costs that occurred during this period of time. (c) Assuming that Manufacturing Overhead has a debit balance of $3,600, determine whether overhead has been under/over applied and make the adjusting entry. (d) Why would Waterways choose
machine hours as the cost driver for the overhead rather than direct labor cost? What would Waterways be likely to choose as the cost driver for the overhead for the job of installing the irrigation system and why?

Need assignment writing services that are 100% risk-free. Our writers are capable of providing the best assignment help to students in globally at best rates.

Assignment online is a team of top-class experts whose only goal is to give you the best assignment help service. Follow the link below to order now...

#write essay #research paper