2024 – EX13 1 Given the diagram shown in figure EX 13 1 with activities A through G

Calculations Shown – 2024

EX13.1        

Given the diagram shown in figure EX 13.1, with activities A through G and duration times,

        

a. Identify the paths and path duration times.

b. Determine the critical path

EX13.3

Calculate ES, LS, EF, LF and slack time for the activities in Exercise 13.1.

Activities Duration Time

A 5

B 7

C 4

D 11

E 3

F 8

G 7

EX13.11

QUESTIONS

a. Calculate the mean duration time for each activity.

b. Calculate the variance for each activity time.

c. Identify the mean and the standard deviation for each path.

d. Calculate project completion probability for 147, 150. And 152 weeks.

 

 

Need assignment writing services that are 100% risk-free. Our writers are capable of providing the best assignment help to students in globally at best rates.

Assignment online is a team of top-class experts whose only goal is to give you the best assignment help service. Follow the link below to order now...

#write essay #research paper