2024 – Given the projected demands for the next six months prepare an aggregate plan that

Given The Projected Demands For The Next Six Months, Prepare An Aggregate Plan That Uses Inventory, Regular Time And Overtime,… – 2024

Given the projected demands for the next six months, prepare an aggregate plan that uses inventory, regular time and overtime, and backorders. Regular time is 150 units per month. Overtime is a maximum of 20 units per month. Overtime cost is $30 per unit, backorder cost is $20 per unit, inventory holding cost is $5 per unit, regular time cost of $20 per unit, and beginning inventory is zero.
Month Forecast
1 180
2 170
3 140
4 150
5 130
6 150

Need assignment writing services that are 100% risk-free. Our writers are capable of providing the best assignment help to students in globally at best rates.

Assignment online is a team of top-class experts whose only goal is to give you the best assignment help service. Follow the link below to order now...

#write essay #research paper