2024 – P18 2 Recognition of Profit on Long Term Contract P18 2 Shanahan Construction Company has entered into a contract beginning January 1

Shanahan Construction Company has entered into a contract beginning January 1, 2014 – 2024

P18-2.  Recognition of Profit on Long-Term Contract)

 

P18-2 Shanahan Construction Company has entered into a contract beginning January 1, 2014, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $900,000. The following data pertain to the construction period.

 

 

2014

2015

2016

Costs to date

$270,000

$450,000

$610,000

Estimated costs to complete

 330,000 

 150,000 

-0-

Progress billings to date

 270,000 

 550,000 

 900,000 

Cash collected to date

 240,000 

 500,000 

 900,000 

Instructions

Using the percentage-of-completion method, compute the estimated gross profit that would be recognized during each year of the construction period.

 

Using the completed-contract method, compute the estimated gross profit that would be recognized during each year of the construction period.

Need assignment writing services that are 100% risk-free. Our writers are capable of providing the best assignment help to students in globally at best rates.

Assignment online is a team of top-class experts whose only goal is to give you the best assignment help service. Follow the link below to order now...

#write essay #research paper