2024 – Problem 1 The following data were obtained from a project to create a new portable electronic Activity

Proj 586 Week 3 Homework | AIB Problems 1 – 4 – 2024

Problem 1

 

The following data were obtained from a project to create a new portable electronic.

 

Activity           Duration         Predecessors 

A                     5 Days             —

B                      6 Days             —

C                     8 Days             —

D                     4 Days             A, B

E                      3 Days             C

F                      5 Days             D

G                     5 Days             E, F

H                     9 Days             D

I                       12 Days           G

 

Step 1: Construct a network diagram for the project. (NOTE: EF for activity H should be 19)

Step 2: Answer the following questions: (15 points total)

 

a)      What is the Scheduled Completion of the Project? (5 points)

b)      What is the Critical Path of the Project? (5 points)

c)      What is the ES for Activity D? (1 points)

d)      What is the LS for Activity G? (1 points)

e)      What is the EF for Activity B? (1 points)

f)        What is the LF for Activity H? (1 points)

g)      What is the float for Activity I? (1 points)

Problem 2

The following data were obtained from a project to build a pressure vessel:

 

Activity           Duration         Predecessors 

A                     6 weeks           —                               

B                      6 weeks           —                               

C                     5 weeks           B                                 

D                     4 weeks           A, C                            

E                      5 weeks           B                                 

F                      7 weeks           D, E, G                       

G                     4 weeks           B

H                     8 weeks           F

I                       5 weeks           G

J                       3 week             I

 

Step 1: Construct a network diagram for the project.

Step 2: Answer the following questions: (15 points total)

 

a)      Calculate the scheduled completion time. (5 points)

b)      Identify the critical path (6 points)

c)      What is the slack time (float) for activity A? (1 points)

d)      What is the slack time (float) for activity D? (1 points)

e) What is the slack time (float) for activity E? (1 points)

f) What is the slack time (float) for activity G? (1 points)

Problem 3

The following data were obtained from a project to design a new software package:

 

Activity           Duration         Predecessors 

A                     5 Days             —                               

B                      8 Days             —                               

C                     6 Days             A                                

D                     4 Days             C, B                            

E                      5 Days             A                                

F                      4 Days             D, E, G                                   

G                     4 Days             B, C

H                     3 Day               G

 

Step 1: Construct a network diagram for the project.

Step 2: Answer the following questions: (15 points total)

 

a)      Calculate the scheduled completion time. (5 points)

b)      Identify the critical path(s) (6 points)

c)      What is the slack time (float) for activity B? (1 points)

d)      What is the slack time (float) for activity D? (1 points)

e) What is the slack time (float) for activity E? (1 points)

f)       What is the slack time (float) for activity G? (1 points)

Problem 4

The following data were obtained from an in-house MIS project:

 

Activity           Duration         Predecessors 

A                     5 Days             —                               

B                      8 Days             —                               

C                     5 Days             A                                

D                     4 Days             B

E                      5 Days             B                                 

F                      3 Day               C, D                

G                     7 Days             C, D

H                     6 Days             E, F, G

I                       9 Days             E, F

 

Step 1: Construct a network diagram for the project.

Step 2: Answer the following questions: (15 points total)

 

a)      Calculate the scheduled completion time. (5 points)

b)      Identify the critical path (6 points)

c)      What is the slack time (float) for activity A? (1 points)

d)      What is the slack time (float) for activity D? (1 points)

e)      What is the slack time (float) for activity E? (1 points)

f)       What is the slack time (float) for activity F? (1 points)

 

Need assignment writing services that are 100% risk-free. Our writers are capable of providing the best assignment help to students in globally at best rates.

Assignment online is a team of top-class experts whose only goal is to give you the best assignment help service. Follow the link below to order now...

#write essay #research paper