The new director of special events at a large university has decided to completely revamp graduation ceremonies. Toward that end, a PERT chart of the major activities has been developed. The chart has five paths with expected completion times and variances as shown in the table. Graduation day is 16 weeks from now.


Path

Expected Duration
(weeks)

Variance

 

A

10                

1.21

 

B

8                

2.00

 

C

12                

1.00

 

D

15                

2.89

 

E

14                

1.44

 


 


Assuming the project begins now, what is the probability that the project will be completed before: (Round your z-value to 2 decimal places and all intermediate probabilities to 4 decimal places. Round your final answers to 4 decimal places.)

 

a.

 

Graduation time?

 


  Probability for graduation time
 

[removed] 

 


 
b.

 

The end of week 15?

 


 
  Probability at the end of week 15

[removed] 

 


 
c.

 

The end of week 13?

 


 
  Probability at the end of week 13

[removed] 

 

                 

 

 

 

Need assignment writing services that are 100% risk-free. Our writers are capable of providing the best assignment help to students in globally at best rates.

Assignment online is a team of top-class experts whose only goal is to give you the best assignment help service. Follow the link below to order now...

#write essay #research paper