Problem 6-5
As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 240 units per eight-hour day. Task times and precedence relationships are as follows: |
Task | Duration (minutes) |
Immediate Predecessor |
a | 0.2 | – |
b | 0.4 | a |
c | 0.2 | b |
d | 0.4 | – |
e | 1.2 | d |
f | 1.2 | c |
g | 1.0 | e, f |
|
Do each of the following: |
b. |
Determine the minimum cycle time, the maximum cycle time, and the calculated cycle time.(Round your answers to 1 decimal place.) |
The minimum cycle time | |
II | |
III | |
IV | |
|
Assignmentsonline.org help students to solve their assignment in the best possible manner. In the assignment help industry, we are regarded as one of the best helpers for students’ tasks in all subjects. We provide solutions to students from all corners of the world, but the main focus is from students residing in the US, UK, and Australia. Our primary focus is solving student assignments for all subjects and streams.