A project has two paths that you are concerned about. The first path (which we will call #1) has an expected path time of 15 weeks and a standard deviation of 3. The second path (#2) has an expected path time of 14 weeks and a standard deviation of 3.4. Which path is critical if the project must be completed within 20 weeks?

 

Answers:

 