Project Management Processes – 2024
The performance of a project was evaluated 10 weeks after its start. Refer to Table 12.15 on page 579 of your textbook for additional details.
- Develop a Gantt Chart based on Table 12.15
- On the same Gantt chart, use a legend to show the project plan and the (actual) project progress.
- Discuss the significance of the two paths or what they mean to the project.